Six large jacks hold up the weight of the bus deck at the Salesforce Transit Center on Monday, Oct. 1, 2018. The jacks sit atop four steel girders and a wooden mat that will be a part of a shoring system that will be installed so that weight will be completely taken off two cracked steel girders that sit above the bus deck. (Kevin N. Hume/S.F. Examiner)

Six large jacks hold up the weight of the bus deck at the Salesforce Transit Center on Monday, Oct. 1, 2018. The jacks sit atop four steel girders and a wooden mat that will be a part of a shoring system that will be installed so that weight will be completely taken off two cracked steel girders that sit above the bus deck. (Kevin N. Hume/S.F. Examiner)

Transit Center fix delays push Fremont Street reopening to next week

Work to shore up the Salesforce Transit Center has hit a snag, delaying the re-opening of Fremont Street until next week.

That’s according to the Transbay Joint Powers Authority, the entity responsible for overseeing the transit center that is leading repairs and analysis after two cracks were discovered in two steel beams in late September. Those cracked beams were directly over Fremont Street, leading the agency’s officials to shore up the transit center with six oversize jacks, much like one would use on a car, to strengthen the building’s foundation.

Initially officials said Fremont Street would reopen by Friday, October 12, but that has now been postponed to Wednesday Oct. 17. The delay is due to “the complexity of the four-level designed shoring system,” the TJPA said in a statement. Work on that shoring system will continue through the weekend and into early next week.

“It is important that we have an extremely robust shoring system to ensure that all levels of the transit center are safe and secure. Unfortunately, this requires us to keep the street closed until this work is complete. We will reopen Fremont Street as soon as safely possible and apologize for the ongoing impact to the public,” said Mark Zabaneh, executive director of the TJPA, in a statement.

The $2.2 billion transit center has been closed since late September. The cracked steel beams were made by Stockton-based Herrick Corp, which also provided the equipment to support the weight of the transit center bus deck.

It is still an open question who will ultimately pay for the transit center’s repairs. Though Zabaneh said publicly the building was under “warranty,” he later told the San Francisco Examiner that ongoing testing — meant to investigate what caused the cracks in the steel beams — would determine who pays. Transit

If you find our journalism valuable and relevant, please consider joining our Examiner membership program.
Find out more at www.sfexaminer.com/join/

Just Posted

Ali Jamalian, whose life was disrupted in the wake of being charged with possession decades ago, now heads up Sunset Connect, a cannabis manufacturing company. (Kevin N. Hume/The Examiner)
Green Rush: Cannabis equity program elevates unexpected entrepreneurs

‘It’s a form of reparations for those of us who were ruined by cannabis arrest’

The Giants and Dodgers face each other again following a May series the Dodgers swept; Dodgers shortstop Gavin Lux caught stealing by Giants second baseman Donovan Solano at Oracle Park on May 23 is pictured. 
Chris Victorio/
Special to The Examiner
Giants vs. Dodgers: What you need to know before this week’s huge series

By Chris Haft Special to The Examiner That grinding noise you’ll hear… Continue reading

San Francisco supervisors approved zoning changes that will allow a chain grocery store to occupy the bottom floor of the 555 Fulton St. condo building. (Kevin N. Hume/The Examiner)
Trader Joe’s approved for Hayes Valley, bringing long-awaited grocery store

New Seasons Market canceled plans at 555 Fulton St. citing construction delays

Most Read