SFPUC plan for green building held up by cost

Lofty city plans to construct an ultra-green windmill-studded, solar-panel-embedded, water-recycling office building near City Hall have been thwarted by growing costs.

Work on the 12-story San Francisco Public Utilities building was slated to begin this year but SFPUC General Manager Ed Harrington announced Tuesday the project will be placed “on hold” because of rising costs.

Moving forward with the project while the SFPUC is spending billions of dollars on seismic improvements might have been unpopular with the agency’s water and electricity customers, who would have borne the construction costs, Harrington said.

The price of planned environmental features in the new building has risen, while detailed analysis has found the benefits of those features would have been lower than originally expected, according to SFPUC spokesman Tony Winnicker.

The solar panels planned for the skin of the building would have added more weight and cost than expected, while shadows would have reduced their effectiveness, according to Winnicker.

jupton@sfexaminer.com

Bay Area NewsLocal

If you find our journalism valuable and relevant, please consider joining our Examiner membership program.
Find out more at www.sfexaminer.com/join/

Just Posted

Man suing SFPD alleging officers beat him with batons

Cop attorney fires back: police were ‘interrupting a dangerous domestic violence incident’

Nuru corruption scandal prompts call to boost Ethics Commission budget

Watchdog agency lacks staff, resources to carry out its duties

Supes to boost subpoena power

Peskin legislation would allow committee to compel testimony under oath

Drug overdose deaths surpass 300 in San Francisco

Three-year rise in fatalities ‘generally driven by fentanyl’

Preston finds support for District 5 navigation center at community meeting

Supervisor hopes to narrow down list of possible locations within months

Most Read