A sign hangs on a barricade outside the shuttered Salesforce Transit Center on Tuesday, Oct. 23, 2018. The transit center was closed after two cracked steel beams were discovered on Sept. 25. (Kevin N. Hume/S.F. Examiner)

A sign hangs on a barricade outside the shuttered Salesforce Transit Center on Tuesday, Oct. 23, 2018. The transit center was closed after two cracked steel beams were discovered on Sept. 25. (Kevin N. Hume/S.F. Examiner)

Preliminary findings expected in Transbay Transit Center cracked beam investigation

The preliminary findings of an investigation into cracked beams that forced the indefinite closure of the Transbay Transit Center are set to be released this week, including lab tests of metal samples.

The findings, which will be announced Thursday at a Transbay Joint Powers Authority meeting, are expected to include metallurgical lab test results of samples from a cracked beam over Fremont Street, the discovery of which led to the center’s abrupt closure in September, as well as a proposed repair plan. A smaller crack was also discovered in a second parallel beam.

The tests will clarify whether the quality of the steel contributed to the cracking.

But they are not expected to answer the question of when the facility will reopen, officials said.

Dennis Turchon, senior construction manager of the project for the TJPA, said that the findings are expected to explain what happened, but may leave unanswered questions that are likely to be presented next month.

“It’s going to talk to what happened. The what,” Turchon said. “Not so much the why.”

Turchon said that they will use the preliminary findings to determine possible repair work for an area over First Street, which has a similar beam but no cracks, and to develop a plan for the review of the entire facility.

“First Street is still getting confirmed what is needed,” he said. “Now with the preliminary findings of what happened you can look at the rest of the structure, the entire Transit Center to determine what else do you need to look at. That now can start being developed.”

The $2.2 billion Transbay Transit Center was closed abruptly in late September, around six weeks after its opening, when cracks in key steel beams were discovered. Since then, in further inspection of the facility “additional fissures have not been found,” according to a Dec. 7 memo from Eric Cordoba, the Transportation Authority Board’s deputy director for capital projects.

San Francisco has assembled a peer review panel of engineers under the Metropolitan Transportation Commission to review the findings and approve next steps. The panel was established at the request of Mayors London Breed and Libby Schaaf.

The San Francisco County Transportation Authority board, which is made up of the 11 members of the Board of Supervisors, were briefed Tuesday on the investigation, but no details were made public.

Supervisor Aaron Peskin, chair of the SFCTA board, called the issue “depressing.”

“The big question here is when and the answer is we don’t know,” Peskin said.

A final report on the “the root cause assessment is anticipated by early January 2019,” Cordoba’s memo states.

When the repair work can be completed and the facility reopen depends largely on how long it will take to procure steel.

The transit center was built through a joint venture between Webcor Builders and Obayashi Corp. Once a planned second phase is completed, the facility is expected to serve as the terminus for both Caltrain and the proposed California high-speed rail project connecting San Francisco to Los Angeles.

However the SFCTA has withheld funding from planning efforts for Phase II, pending increased oversight, including assembling an outside panel of experts to review the plans. “We anticipate completing the selection of panel experts by January 4, 2019 and completing the effort by May 2019,” said Cordoba’s memo. Transit

If you find our journalism valuable and relevant, please consider joining our Examiner membership program.
Find out more at www.sfexaminer.com/join/

Just Posted

Gov. Gavin Newsom, show here speaking at the City College of San Francisco mass vaccination site in April, faces a recall election due to anger on the right over his handling of the pandemic, among other issues. (Kevin N. Hume/S.F. Examiner)
Why Gavin Newsom’s popularity could work against him in the recall election

Top pollster: ‘We’re not seeing the Democrats engaged in this election. And that may be a problem…’

Passengers ride the 14-Mission Muni bus on Friday, March 12, 2021. (Jordi Molina/Special to S.F. Examiner)
Transit officials fear Free Muni pilot could hurt already-strained service levels

Supporters say fare cuts could increase ridership, help low-income residents

The vacant property at 730 Stanyan St. in the Haight currently houses a safe sleeping site for the homeless. <ins>(Kevin N. Hume/S.F. Examiner)</ins>
Affordable housing project on former McDonald’s site delayed as city adds units

The start of construction on an affordable housing project on the site… Continue reading

Visitors read a notice hanging on the Polk Street entrance to City Hall on Thursday, March 26, 2020, shortly after the building was closed. (Kevin N. Hume/S.F. Examiner)
City Hall reopening to the public on June 7 after long closure due to COVID-19

San Francisco will reopen City Hall to the public on June 7… Continue reading

Historic streetcars are undergoing testing on The Embarcadero to prepare for their return to service on May 15.<ins></ins>
What to expect for Muni Metro’s relaunch on May 15

Significant service restoration includes downtown subway tunnels and historic streetcars

Most Read