Golden Gate Bridge seismic retrofit the largest project since original construction

Golden Gate Bridge Chief Engineer Ewa Bauer calls it “the largest undertaking in the history of the bridge since its construction.” Bridge district spokeswoman Mary Currie, who has been with the district for 20 years and is one of its foremost historians, says the seismic retrofit is “the most important project” among a series of renovations dating back to the early 1950s.

It’s also the most expensive, by far. Approximately $400 million has been spent reinforcing the bridge since 1997, and another $200 million still needs to be secured to finish the final phase, which should begin within two years and wrap up between 2016 and 2018.

#link_box { width: 150px; height: auto; margin: 0; padding: 0; margin: 10px 20px 10px 0px; padding: 10px; background-color: #fbfade; /* ecru – light yellow */ border: 1px solid #343a25; /* green – for summer arts */ float: left; font-family: arial, sans serif; font-size: 11px; } #link_box img, #link_box a { border 0px; border-style: none; outline: none; } #link_box h1 { margin: 0; padding: 5px; border-bottom: 1px solid #ddd; text-transform: uppercase; color: #000; font-family: arial, sans serif; font-weight: bold; font-size: 12px; text-align: center; } #link_box ul { list-style: none; margin: 0; padding: 0; border: none; } #link_box li { margin: 0px padding: 0px; border-bottom: 1px solid #ddd; border-bottom-width: 1px; } #link_box li a { display: block; padding: 5px 5px 5px 15px; /* Padding for bullet */ /* border-bottom: 1px solid #ddd; border-bottom-width: 1px; */ color: #000; width: 100%; width: auto; /* height: auto; */ /* border: 1px solid blue; */ margin: 0px; font-family: arial, sans serif; font-size: 11px; line-height: 14px; text-decoration: none; } #link_box li a: before { /* background-position: top left; */ } #link_box li a:hover { background-color: #ddd; color: #000; }

By those metrics, the 20-year, $660 million project surpasses even the original construction, which required only four years and $35 million ($564 million in today’s dollars).

The Golden Gate Bridge, Highway and Transportation District set out to retrofit the span in response to the 6.9-magnitude Loma Prieta earthquake of 1989, which collapsed a section of the upper deck of the Bay Bridge, yet left the Golden Gate Bridge unharmed.

The difference was due less to how they were built than where: The Bay Bridge sits on soft bay mud and the Golden Gate Bridge on solid rock.

Still, engineers determined the bridge needed additional lateral support to survive an even larger event and decided to retrofit the landmark to withstand what’s known as a “maximum credible earthquake.”

That translates to about 8.3 on the Richter scale, greater than the 1906 temblor that leveled The City. The bridge was originally designed to withstand about 7.5 percent of its weight in horizontal forces, Bauer said, and today, after retrofitting, the same measure for the south anchorage housing — a critical component of the bridge foundation — is 220 percent.

Phase 3 of the project, under way since 2008, involves strengthening the north anchorage housing and replacing a portion of the roadway deck with 78 new concrete-on-steel panels measuring 25-by-10 feet and weighing approximately 41,000 pounds each; they’ll help the underlying anchorage housing withstand massive quakes by sharing some of the load.

Once the final $200 million infusion is approved by Congress, the bridge’s iconic 1.2-mile suspension span will be strengthened over the course of three or four years. None of the work will alter the appearance of the bridge in any way, Bauer said, and it’s something she takes great pride in. Still, she’s itching to see it complete.

“In my mind,” she said, “the most important thing I have is to get this job done.”

The nuts and bolts of the bridge

  • Length including approaches: 1.7 miles
  • Length of suspension span: 1.2 miles
  • Bridge width: 90 feet
  • Clearance above high water: 220 feet
  • Deepest foundation below mean low-water level: 110 feet
  • Height of towers above water: 746 feet
  • Side-to-side sway at center span: 28 feet
  • Up-and-down sway at center span: 17 feet
  • Vertical suspender ropes: 500
  • Diameter of bridge cables: 363⁄8 inches
  • Wires in each cable: 27,752
  • Length of one cable: 7,650 feet
  • Total length of wire used: 80,000 miles
  • Strands in each cable: 61
  • Lamp posts: 128
  • Rivets in towers: 120,000
  • Gallons of paint applied each year: 10,000-30,000
  • Cubic yards of concrete (original construction): 389,000
  • Tons of structural steel (original construction): 83,000
  • Total weight of bridge (original construction): 887,000 tons

 

Bay Area NewsLocalTransittransportation

If you find our journalism valuable and relevant, please consider joining our Examiner membership program.
Find out more at www.sfexaminer.com/join/

Just Posted

Giants second baseman Donovan Solano scores on a double in the seventh inning against the Dodgers at Oracle Park on July 29. (Chris Victorio/Special to The Examiner)
Will the Giants make the playoffs? Kris Bryant may be the answer

By Chris Haft Special to The Examiner You’d be hard-pressed to find… Continue reading

Tiffany Carter, owner of Boug Cali West Coast Creole Shack in San Francisco’s La Cocina Marketplace, was dismayed by gentrification she found when she returned to her hometown to start a business. (Kevin N. Hume/The Examiner)
SF Black Wallstreet: Helping residents build wealth, reclaim spaces they’ve had to leave

Tiffany Carter moved back to her hometown of San Francisco five years… Continue reading

A prescribed fire at Sequoia and Kings Canyon National Parks was conducted in June 2016 to reduce hazardous fuel loading, increase watershed health, and restore the natural fire cycle in the Redwood Canyon area ecosystem. (Photo courtesy Rebecca Paterson/National Park Service)
Experts, UC scientists discuss wildfires in the state’s riskiest regions

Wildfires are nothing new in California’s history, but the magnitude and frequencies… Continue reading

Fourth-grade students at Lucerne Valley Elementary School don masks and Western wear for a “Walk Through California” history day during in-person instruction. (Courtesy of Krystal Nelson)
Confusion over mask mandate for California schools sparks tension between districts and parents

By Diana Lambert EdSource Shifting rules around mask mandates at schools are… Continue reading

Steven Buss, left, and Sachin Agarwal co-founded Grow SF, which plans to produce election voter guides offering a moderate agenda. (Kevin N. Hume/The Examiner)
Grow SF: New tech group aims to promote moderate ideals to political newcomers

Sachin Agarwal has lived in San Francisco for 15 years. But the… Continue reading

Most Read