Central Subway tunnel boring machines will live on

Tunnel-boring machines Big Alma and Mom Chung might be finished with Muni's Central Subway project, but they have thousands of feet left in their arsenals. Upon refurbishment, they would be suitable for more local projects, such as extending the subway farther or building tunnels for BART's extension to San Jose.

When Big Alma broke through the ground last week, and at an event Monday with city officials celebrating the end of tunneling, its cutter head appeared more worn out than that of Mom Chung, which surfaced June 2. Each machine carved through 8,500 feet of rock and soil, but both finished in “beautiful shape,” said Sarah Wilson, resident engineer representing the San Francisco Municipal Transportation Agency.

Big Alma likely encountered more abrasive ground, or the tunnel-boring crew elected not to change its cutters and scrapers because the last stretch was primarily soil.

“I don't think they will have any trouble reusing the machines,” Wilson said. “They just will need to put a new set of cutters on.”

As typically happens in the construction world, the contractor — in the Central Subway's case, it is Barnard Impregilo Healy — resells the tunnel-boring machine to the manufacturer, The Robbins Co., to refurbish and make available for other projects.

Already, interest has been expressed for refurbished Big Alma and Mom Chung from around the world, according to Central Subway head tunnel design engineer Matt Fowler.

On another note, the machines, with approximately 20-foot diameters, are very well-suited size-wise for BART's extension to San Jose, Fowler, 57, said.

“It would be wonderful,” he said. “It's not unheard of that they stay close to home.”

BART is currently building more track south from Fremont and into northern San Jose, with the goal of one day going into the downtown area. For a future project, 5 miles of the BART extension in San Jose would require underground tunneling, although designs are still being refined. If the refurbished Central Subway tunnel-boring machines meet the criteria for BART, they “certainly would be worth considering,” said Bernice Alaniz, a spokeswoman for the Santa Clara Valley Transportation Authority, which is building the extension because it is out of BART's district.

An extension of the Central Subway to Fisherman's Wharf is being studied. But even if that moves forward, Big Alma and Mom Chung are not designed to make a turn that would be necessary for the project.

For now, the machines need to be extracted from the retrieval shaft at the old Pagoda Theater in North Beach.

Big Alma will be the first to go. A tunnel-boring machine cradle will be installed at the bottom of the retrieval shaft and Big Alma will be pushed 16 feet out. Its cutter head will be sliced in half and removed with a crane. The remainder of the machine will also be taken apart for removal.

Mom Chung will follow, and both machines — named after historic San Francisco women — should be fully disassembled within 16 weeks.

Bay Area NewsCentral SubwayMuniSan Francisco Municipal Transportation AgencyTransittransportation

If you find our journalism valuable and relevant, please consider joining our Examiner membership program.
Find out more at www.sfexaminer.com/join/

Just Posted

Passengers ride the 14-Mission Muni bus on Friday, March 12, 2021. (Jordi Molina/Special to S.F. Examiner)
Transit officials fear Free Muni pilot could hurt already-strained service levels

Supporters say fare cuts could increase ridership, help low-income residents

The vacant property at 730 Stanyan St. in the Haight currently houses a safe sleeping site for the homeless. <ins>(Kevin N. Hume/S.F. Examiner)</ins>
Affordable housing project on former McDonald’s site delayed as city adds units

The start of construction on an affordable housing project on the site… Continue reading

Visitors read a notice hanging on the Polk Street entrance to City Hall on Thursday, March 26, 2020, shortly after the building was closed. (Kevin N. Hume/S.F. Examiner)
City Hall reopening to the public on June 7 after long closure due to COVID-19

San Francisco will reopen City Hall to the public on June 7… Continue reading

Historic streetcars are undergoing testing on The Embarcadero to prepare for their return to service on May 15.<ins></ins>
What to expect for Muni Metro’s relaunch on May 15

Significant service restoration includes downtown subway tunnels and historic streetcars

San Francisco 49ers quarterback Jimmy Garoppolo (10) and running back Raheem Mostert (31) celebrate after Mostert scores his fourth rushing touchdown in the third quarter as the 49ers take on the Green Bay Packers in the NFC Championship game at Levi’s Stadium in Santa Clara, Calif. on Sunday, Jan. 19, 2020. (Kevin N. Hume/S.F. Examiner)
49ers on prime-time TV five times in 2021

Usually a team that finishes in last place and won only six… Continue reading

Most Read