Bridge-fix dry run finds minor glitch

A possible disruption to the Bay Bridge retrofit project was averted and crews were able to get back on schedule Thursday morning after preliminary tests showed there was not enough power to lift and replace a section of the span.

The bridge is being shut down from 8 p.m. today until 5 a.m. Tuesday to allow construction workers time to work on replacing a portion damaged in the 1989 Loma Prieta earthquake.

Two of the 16 computer-controlled hydraulic jacks that will lift the new section failed to provide enough power during a test Wednesday night, Caltrans Bay Bridge retrofit project spokesman Bart Ney said.

Crews had underestimated the size of the heaviest end of the viaduct and used more pressure during atest Thursday at 10 a.m. to fix the malfunction.

The jacks are required to move the new 350-foot Yerba Buena viaduct onto the lower deck in the area connecting the Yerba Buena Island tunnel to the new eastern span. Ney said the process takes 13 to 15 hours in the latter stages of the project, and the glitch could have delayed the reopening of the bridge.

The $40 million bridge construction should go as planned, and the seismically retrofitted bridge will be ready for drivers by Tuesday at 5 a.m., Ney said.

“That’s the reason why we do these types of tests,” Ney said. “We’re in great shape with the jacks.”

The crew will have backup machinery, so the likelihood of the bridge not opening on time Tuesday is small, Ney said.

The new section should last about 150 years. Crews first need to demolish the existing roadway and clean up the debris, which will take about 43 hours.

“It’s going to look at the same as it does now, except that it will be seismically safe,” Metropolitan Transportation Commission spokesman John Goodwin said. “The changes that will be visible will be at the toll plaza, where there will be changes to the FasTrak lane configuration,” which will have about 2,000 feet of extended striping.

The next scheduled Bay Bridge closure will be in approximately 18 months, Ney said.

mrosenberg@examiner.com

Bay Area NewsLocalTransittransportation

If you find our journalism valuable and relevant, please consider joining our Examiner membership program.
Find out more at www.sfexaminer.com/join/

Just Posted

Salesforce Tower in San Francisco, which features a comprehensive water-recycling system, on July 30, 2021. Water recycling in office buildings is seen as a promising sustainability effort, as well as a smart hedge against rising costs and future shortages. (Jim Wilson/The New York Times)
Salesforce Tower is part of a nationwide water recycling trend: Here’s how it works

By Patrick Sisson New York Times When Salesforce Tower in San Francisco… Continue reading

Folks wave from the side of a Muni cable car as it heads down Powell Street after cable car service returns from a 16-month COVID absence on Monday, Aug. 2, 2021. (Kevin N. Hume/The Examiner)
San Francisco’s cable cars return after 16-month absence

San Francisco’s cable cars are back, and they’re free for passengers to… Continue reading

An East Palo Alto resident is inoculated during a COVID-19 vaccination clinic run by Ravenswood Family Health Network at Facebook headquarters in Menlo Park on April 10, 2021. (Photo by Anne Wernikoff, CalMatters)
COVID vaccinations lag for people on Medi-Cal

By Ana B. Ibarra CalMatters Low-income Californians enrolled in Medi-Cal have been… Continue reading

Most Read