Mission Playground renovations? Delayed 18 months. Chinese Recreation Center upgrades? Delayed 24 months. McCoppin Square improvements? Delayed four months.
In fact, every one of the 12 park improvement projects funded by a 2008 voter-approved bond have been delayed, according to a July quarterly report. On average, the projects are now projected to finish about 14 months after originally promised.